Home » Jasa Instalasi EI Elektrikal Pembangkit Listrik PLTU PLTGU

Jasa Instalasi EI Elektrikal Pembangkit Listrik PLTU PLTGU

JASA INSTALASI E&I

Jasa Instalasi Elektrikal Pembangkit Listrik
PLTU · PLTGU · PLTA · PLTM — Generator, Trafo, Switchgear 150kV

PT TEM menyediakan jasa instalasi elektrikal dan instrument di fasilitas pembangkit listrik tenaga uap (PLTU), gas (PLTGU), air (PLTA), dan energi baru terbarukan (EBT). Pengalaman di berbagai PLTU captive power industri dan pembangkit PLN dari Jawa hingga Indonesia Timur.

🏗️
EPC Capable
Supply, install, commissioning
👷
Tenaga Ahli
SKTTK, BNSP, SLO certified
📋
Dokumen Resmi
As-built drawing, test report
🔧
Garansi Kerja
Workmanship guarantee

Lingkup Instalasi Elektrikal Power Plant

Pembangkit listrik memerlukan instalasi elektrikal presisi tinggi, mulai dari sisi generator, trafo unit, switchgear, hingga relay proteksi diferensial dan excitation system.

Lingkup Pekerjaan:

  • Instalasi generator (stator, rotor, exciter)
  • Pemasangan trafo unit (generator transformer)
  • Instalasi switchgear 150kV (GIS atau AIS)
  • Panel relay proteksi generator (87G, 64F, 40Q)
  • Instalasi sistem eksitasi (excitation system)
  • Bus duct dan kabel daya 11kV/6.6kV generator
  • Sistem auxiliary power (station service transformer)
  • Battery dan battery charger DC system 110V
  • Instalasi SCADA dan control panel DCS
  • Cable tray, grounding, dan lightning protection

Standar yang Diterapkan:

IEC 60034 (Generator)IEC 60076 (Trafo)IEEE C37 (Switchgear)IEC 61850 (SCADA)IEC 61511 (SIS)PLN SPLN D3.001

Klien/Proyek yang Dilayani:

  • PLTU captive power smelter (IMIP, IWIP, VIRTUE DRAGON)
  • PLTU IPP (Independent Power Producer)
  • PLTM dan PLTA (hidro minihydro)
  • PLTS (photovoltaic utility scale)
  • PLN pembangkit Indonesia Timur

Tahapan Pelaksanaan Pekerjaan Instalasi

1
Single Line Diagram & Protection Philosophy Review
Review SLD, relay coordination study, seting relay proteksi generator dan trafo

2
Material Inspection (FAT)
Factory Acceptance Test generator, trafo, switchgear sebelum mobilisasi ke site

3
Civil Work Coordination
Koordinasi pondasi generator, trafo yard, dan cable trench dengan kontraktor sipil

4
Mechanical & Electrical Installation
Erection dan setting generator stator/rotor, instalasi trafo unit, switchgear

5
Bus Duct & High Voltage Cabling
Instalasi bus duct generator, kabel HV 11kV/6.6kV, cable termination

6
Relay & Control Panel Wiring
Wiring panel relay proteksi, DCS, SCADA, system control and protection

7
Pre-commissioning Test
Megger, TTR trafo, winding resistance, CB timing, excitation test (no-load)

8
Commissioning (Load Test)
Load bank test generator, paralleling test, full load test 100%

9
COD (Commercial Operation Date)
Witnessing PLN/owner, issuance COD certificate, serah terima aset

Referensi Proyek Instalasi PT TEM

PLTU Suralaya 9-10 (Banten)
Testing generator dan trafo daya pembangkit 660MW
PLTU Captive Smelter Morowali
Instalasi dan commissioning generator captive power smelter nikel
PLTU Captive Halmahera (IWIP)
T&C sistem elektrikal pembangkit IWIP Weda Bay
PLTM/PLTA Kalimantan
Commissioning generator minihydro remote area
PLTB/PLTS Energi Terbarukan
Testing dan commissioning inverter grid-tie EBT
PLTGU IPP Jawa
Commissioning switchgear 150kV dan relay proteksi

Dukungan Testing & Commissioning Setelah Instalasi

PT TEM adalah satu-satunya kontraktor EI di Indonesia Timur yang menyediakan layanan full-package: dari instalasi hingga testing & commissioning. Setelah instalasi selesai, tim T&C kami langsung melakukan pengujian dengan alat milik sendiri — tidak perlu mobilisasi kontraktor lain.

Butuh Kontraktor Instalasi Elektrikal yang Terpercaya?

PT TEM: Satu paket — supply material, instalasi, testing, commissioning, laporan resmi. Dari Balikpapan ke seluruh Indonesia.

WA: 0812-9708-3589 | marketing@tridayaelektramandiri.com

💬 Tanya Tim PT TEM Kami siap bantu informasikan:
Scroll to Top