Commissioning panel MV switchgear adalah tahap kritis sebelum energizing. Berikut checklist dan prosedur lengkap sesuai standar IEC 62271.
Pre-Commissioning Visual Check
- Verifikasi single line diagram vs as-built
- Cek nameplate semua equipment
- Visual inspection kebersihan, kabel terminasi, label
- Verifikasi grounding sistem switchgear
- Cek mekanik: pintu, shutter, interlock
Pengujian Utama
1. Insulation Resistance Test
Megger test 2500V atau 5kV pada semua bus, feeder, dan incoming. Nilai minimum 1000 MOhm untuk switchgear baru.
2. Hi-Pot (Withstand Test)
Sesuai IEC 62271-200. Tegangan uji: 2 x Un + 1000V selama 1 menit.
3. Circuit Breaker Test
| Pengujian | Parameter | Standar |
|---|---|---|
| Contact resistance | Mikro-ohm meter | Sesuai pabrikan |
| Insulation resistance | Min 1000 MOhm | IEC 62271 |
| Operating time OPEN | Sesuai nameplate | Timing test |
| Operating time CLOSE | Sesuai nameplate | Timing test |
| Minimum trip voltage | Min 70% Vn | IEC 60255 |
4. Protection Relay Testing
Test pickup, time-current, dan instantaneous menggunakan Omicron CMC 356. Verifikasi setting sesuai koordinasi proteksi yang disetujui.
5. Interlocking Test
Verifikasi semua mekanik dan elektrik interlock bekerja benar: key interlock, shutter, earth switch, bus interlock.
Energizing Procedure
- Semua test completed dan sign-off engineer
- Remove temporary grounding
- Clear area – safety perimeter established
- Energize step by step: incoming, bus, feeder
- Monitor arus, tegangan, dan suhu
Konsultasi & Jasa Pengujian
PT Tridaya Elektra Mandiri melayani seluruh Indonesia.
Butuh Alat atau Jasa Terkait?
PT Tridaya Elektra Mandiri siap membantu — alat terkalibrasi, operator bersertifikat, seluruh Indonesia