Commissioning PLTS industri memerlukan prosedur sistematis untuk performa optimal dan keamanan operasi. Berikut panduan step-by-step lengkap.
Scope Commissioning PLTS
- Solar PV modules dan string combiner box
- DC cabling dan proteksi
- String inverter atau central inverter
- AC panel dan grid connection
- BESS – Battery Energy Storage System
- Monitoring dan SCADA
Step 1: Pre-Commissioning Solar PV
| Item | Pengujian | Nilai Normal |
|---|---|---|
| Module Voc | Multimeter | Sesuai datasheet plus/minus 3% |
| String polarity | Cek positif dan negatif | Harus benar |
| Insulation DC | Megger 1kV | Min 1 MOhm/kW |
| String Isc | Clamp meter | Sesuai datasheet |
Step 2: Inverter Commissioning
- Setting grid parameter: frekuensi 50Hz, tegangan 380V, cos phi
- Setting proteksi: anti-islanding, OVR, UVR, OFR, UFR
- Test fungsi MPPT
- Test export limit sesuai aturan PLN
Step 3: BESS Commissioning
- Cell balancing check
- BMS parameter setting
- Charge dan discharge cycle test
- Protection test: OVP, UVP, OCP, thermal protection
Step 4: Grid Connection dan Power Quality
- Sinkronisasi tegangan dan fasa
- Power quality measurement: harmonik THD, power factor
- Test proteksi grid code PLN
- Performance ratio measurement
Standar Acuan
IEC 62446-1 (dokumentasi PLTS), IEC 62109 (keamanan inverter), IEC 61427 (BESS), SNI dan PERMEN ESDM tentang PLTS.
Konsultasi & Jasa Pengujian
PT Tridaya Elektra Mandiri melayani seluruh Indonesia.
Butuh Alat atau Jasa Terkait?
PT Tridaya Elektra Mandiri siap membantu — alat terkalibrasi, operator bersertifikat, seluruh Indonesia