Commissioning PLTS Industrial Step by Step – Solar Panel, Inverter, BESS

Commissioning PLTS industri memerlukan prosedur sistematis untuk performa optimal dan keamanan operasi. Berikut panduan step-by-step lengkap.

Scope Commissioning PLTS

  • Solar PV modules dan string combiner box
  • DC cabling dan proteksi
  • String inverter atau central inverter
  • AC panel dan grid connection
  • BESS – Battery Energy Storage System
  • Monitoring dan SCADA

Step 1: Pre-Commissioning Solar PV

ItemPengujianNilai Normal
Module VocMultimeterSesuai datasheet plus/minus 3%
String polarityCek positif dan negatifHarus benar
Insulation DCMegger 1kVMin 1 MOhm/kW
String IscClamp meterSesuai datasheet

Step 2: Inverter Commissioning

  • Setting grid parameter: frekuensi 50Hz, tegangan 380V, cos phi
  • Setting proteksi: anti-islanding, OVR, UVR, OFR, UFR
  • Test fungsi MPPT
  • Test export limit sesuai aturan PLN

Step 3: BESS Commissioning

  • Cell balancing check
  • BMS parameter setting
  • Charge dan discharge cycle test
  • Protection test: OVP, UVP, OCP, thermal protection

Step 4: Grid Connection dan Power Quality

  • Sinkronisasi tegangan dan fasa
  • Power quality measurement: harmonik THD, power factor
  • Test proteksi grid code PLN
  • Performance ratio measurement

Standar Acuan

IEC 62446-1 (dokumentasi PLTS), IEC 62109 (keamanan inverter), IEC 61427 (BESS), SNI dan PERMEN ESDM tentang PLTS.

Konsultasi & Jasa Pengujian

PT Tridaya Elektra Mandiri melayani seluruh Indonesia.

WhatsApp: 0812-9708-3589

Butuh Alat atau Jasa Terkait?

PT Tridaya Elektra Mandiri siap membantu — alat terkalibrasi, operator bersertifikat, seluruh Indonesia

💬 Tanya Tim PT TEM Kami siap bantu informasikan:
Scroll to Top