Home » Testing Commissioning HV Apparatus Relay Protection Gardu Induk 150kV — Tahapan IK, Alat Uji CB CT Relay | PT TEM


⚡ HV Apparatus Testing 150kV
🔴 Relay Protection — Secondary & Primary Injection
📋 SPLN T5.005 · IEC 62271 · IEC 61869
🏭 PLN · Pertamina · IMIP · PTFI

Testing Commissioning HV Apparatus & Relay Protection
Gardu Induk 150kV — Tahapan IK, Alat Uji CB · CT · Relay | PT TEM

Panduan lengkap dan referensi lapangan testing commissioning gardu induk 150kV: dari pre-commissioning test, relay protection secondary injection, primary injection CT, CB timing, CVT tan delta, baterai DC, hipot resonant, hingga energize pertama. PT TEM telah mengerjakan T&C GI 150kV di Kalimantan, Sumatera, Jawa, Sulawesi, dan Papua.

Standar & Regulasi

Mengapa Testing Commissioning HV Apparatus GI 150kV Tidak Boleh Dilewatkan?

Gardu induk 150kV adalah titik kritis infrastruktur tenaga listrik. Satu relay yang salah setting, satu CT dengan rasio tidak terverifikasi, atau satu circuit breaker dengan waktu trip yang tidak akurat — dapat berakibat busbar fault yang tak tertangani, kerusakan trafo senilai ratusan miliar, atau blackout regional.

Testing commissioning (T&C) HV apparatus dan relay protection GI 150kV wajib dilaksanakan karena:

  • PLN mensyaratkan T&C sebelum izin operasi GI diterbitkan (SPLN T5.005)
  • Relay yang baru di-install harus diverifikasi secara independen dari setting proteksi PLN Pusat
  • CT ratio error dapat membuat relay trip terlalu dini atau terlambat → kerusakan peralatan
  • CB timing yang meleset dapat memperpanjang fault clearing time → risiko busbar damage
  • GIS membutuhkan verifikasi SF6 dan partial discharge sebelum pemberian tegangan
  • Sistem baterai DC yang tidak terverifikasi adalah risiko total loss of protection saat PLN padam
📋 Regulasi & Standar yang berlaku:
SPLN T5.005:2018 (PLN Prosedur T&C GI) · IEC 62271 (HV Switchgear) · IEC 61869 (CT/VT) · IEC 60255 (Relay Protection) · IEEE C57.13 (CT) · IEEE C37 (CB) · IEC 62440/60840 (GIS & Kabel HV)

PT TEM melakukan pengujian HV apparatus di switchyard 150kV — verifikasi CT dan peralatan tegangan tinggi sebelum energisasi

PT TEM melakukan pengujian HV apparatus di switchyard 150kV — verifikasi CT dan peralatan tegangan tinggi sebelum energisasi

Tahapan Pekerjaan

7 Tahapan Testing Commissioning Gardu Induk 150kV Sesuai SPLN T5.005 & IEC

PT TEM melaksanakan T&C GI 150kV mengikuti prosedur SPLN T5.005 PLN yang dipadukan dengan best practice IEC internasional. Setiap tahap memiliki acceptance criteria yang harus dipenuhi sebelum melanjutkan ke tahap berikutnya.

1

Pre-Commissioning Test — Verifikasi Peralatan Sebelum Tegangan

Sebelum tegangan apapun dimasukkan, semua HV apparatus diverifikasi secara individu: insulation resistance test (megger 5kV/10kV) semua terminal CB, CT, VT, busbar, kabel; contact resistance test (DLRO) CB dan disconnector; SF6 gas pressure check di semua kompartemen GIS; visual inspection dan dimensional check sesuai GAD; grounding system verification.

2

CT & VT Testing — Verifikasi Rasio, Burden, dan Akurasi

Semua CT (Current Transformer) dan VT (Voltage Transformer) diuji secara individual: ratio test menggunakan CPC 100 atau CT Analyzer (verifikasi tap ratio ±0.1%), burden test (beban sekunder vs rated burden), excitation curve (knee point voltage), polarity check, dan phasing test tiga fasa. CT kelas proteksi 5P20/10P20 harus memenuhi accuracy limit factor sesuai IEC 61869-2.

3

Relay Protection Testing — Secondary Injection Test (Omicron CMC 356)

Ini adalah tahap paling kritikal. Semua relay proteksi diuji via secondary injection menggunakan Omicron CMC 356: pickup test (arus/tegangan pickup ±5%), timing test (TDS curve IDMT), instantaneous test, directional test (distance relay), differential stability dan operate test, frequency relay test, dan GOOSE test untuk relay IEC 61850. Setiap relay mendapat test report individual.

4

Primary Injection Test — End-to-End Verification (CPC 100 + CPTD)

Setelah secondary injection, primary injection dilakukan untuk membuktikan chain CT → kabel pilot → relay berfungsi end-to-end. CPC 100 menyuntikkan arus primer melalui CT sebenarnya — relay harus trip sesuai setting. Ini membuktikan tidak ada wiring error, CT polaritas benar, dan sistem proteksi berfungsi sebagai satu kesatuan.

5

Circuit Breaker Testing — Timing, Travel, dan Contact Resistance

CB 150kV diuji menggunakan CB analyzer: operation time (close/trip/reclose sesuai IEC C37.09), contact travel measurement, contact resistance (DLRO <100μΩ), SF6 pressure, dan minimum trip voltage test. Untuk CB 500kV atau GIS CB, tambahkan coil continuity test dan wiring interlocking verification.

6

DC System & Baterai Testing — Power Supply untuk Relay & Kontrol

Sistem DC 110V/220V adalah tulang punggung operasi relay dan kontrol GI. Testing: battery capacity test (discharge 10-hour rate), charger output test, DC distribution check, insulation resistance DC system, alarm dan indikasi level baterai, dan verifikasi UPS/inverter backup. Baterai yang tidak terverifikasi adalah risiko catastrophic loss of protection saat PLN padam.

7

Hipot Test, Functional Test & Energize — Final Commissioning

Hipot test dilakukan pada kabel MV dan busbar GIS menggunakan VLF (Very Low Frequency) atau resonant hipot sesuai IEC 60840. Kemudian functional test interlocking, SCADA communication test, dan alarm verification. Terakhir: step energize bertahap dipantau bersama PLN — trafo NO-load → line charging → full energize dengan semua proteksi aktif.

Primary injection test menggunakan Omicron CPC 100+CPTD di gardu induk 150kV — PT TEM verifikasi CT dan relay end-to-end

Primary injection test menggunakan Omicron CPC 100+CPTD di gardu induk 150kV — PT TEM verifikasi CT ratio dan relay protection end-to-end

Arsenal Alat Uji

Alat Uji PT TEM untuk T&C Gardu Induk 150kV

PT TEM memiliki armada alat uji HV apparatus lengkap yang dioperasikan oleh engineer bersertifikat. Semua unit terkalibrasi BSML dan siap mobilisasi ke seluruh Indonesia.

Omicron CMC 356

6-phase relay test set universal. Secondary injection test semua relay digital (SIPROTEC, REF615, SEL, Sepam). Support IEC 61850 GOOSE.

→ Relay protection testing

Omicron CPC 100 + CPTD

Primary injection tester. Uji CT ratio, excitation curve, burden, dan end-to-end relay trip test. Output arus primer hingga 2000A.

→ CT testing & primary injection

CB Analyzer

Circuit breaker timing analyzer. Operation time, contact travel, coil diagnostics. Kompatibel semua CB 150kV/500kV.

→ CB timing & travel test

DLRO (Micro-Ohmmeter)

Contact resistance measurement CB main contact, disconnector, busbar joint. Resolusi 0.1μΩ, arus test hingga 200A.

→ Contact resistance test

Hipot Resonant 500kV

AC hipot test kabel 150kV dan GIS busbar sesuai IEC 60840 dan IEC 62271. Frekuensi variable 20–300Hz, mobile unit.

→ Hipot test kabel & GIS

VLF Hipot Tester

Very Low Frequency hipot test untuk kabel MV 20kV dan GIS 150kV. Alternating sebagai pengganti DC hipot sesuai IEC 60060-3.

→ Cable & GIS hipot test

Megger 5kV / 10kV

Insulation resistance test CB, CT, VT, kabel, trafo. Guard terminal untuk eliminasi surface leakage. Log IR dan PI value.

→ Insulation resistance test

Battery Discharge Tester

Battery capacity test sistem DC GI. Discharge 10-hour rate, kapasitas aktual vs nominal, cell voltage monitoring real-time.

→ DC battery capacity test

Secondary injection test relay proteksi Siemens SIPROTEC di ruang panel gardu induk 150kV — tim PT TEM commissioning relay

Secondary injection test relay Siemens SIPROTEC di ruang panel GI 150kV — tim PT TEM menggunakan Omicron CMC 356

Hipot test resonant 500kV untuk kabel bawah tanah dan GIS — PT TEM melakukan AC hipot test sesuai IEC 60060 dan IEC 60840

Hipot resonant test 500kV untuk kabel bawah tanah HV dan GIS — PT TEM melakukan AC hipot test sesuai IEC 60840

Relay Protection Testing

Relay Protection Testing GI 150kV — Jenis, Standar, dan Parameter Uji

Relay protection adalah sistem pertahanan gardu induk dari gangguan. Setiap relay memiliki fungsi spesifik dan acceptance criteria tersendiri. Berikut matriks lengkap relay yang diuji PT TEM beserta standarnya:

Secondary injection test relay di panel proteksi gardu induk PLN — PT TEM menggunakan Omicron CMC 356 dan software Test Universe

Secondary injection test relay di panel proteksi GI 150kV PLN — Omicron CMC 356 + software Test Universe

Testing relay protection menggunakan Megger Sverker 900 di panel switchgear — PT TEM melakukan verifikasi relay overcurrent dan earth fault

Testing relay protection dengan Megger Sverker 900 — verifikasi relay overcurrent dan earth fault panel switchgear

Kode ANSIFungsi RelayParameter Uji UtamaAcceptance Criteria
50/51Overcurrent & IDMTPickup (Is), time multiplier (TDS), curve shape, instantaneousPickup ±5%, timing ±10ms atau ±5%
50N/51NEarth Fault (Ground OC)Zero sequence pickup, directional (67N), sensitif groundSama dengan 50/51, directional test ±5°
87TDifferential TransformerOperate vs restraint region, bias slope, stabilitas arus inrushOperate: ±5% dari setting; Restraint: tidak trip saat external fault
87BBusbar DifferentialZone check, current summation, high impedance stabilityStabilitas ±2%, operate sesuai differential current threshold
87LLine Differential (POTT)Local + remote current, communication channel (fiber/pilot)Trip waktu <30ms; tidak trip saat luar zone
21Distance RelayZone 1/2/3 impedance reach, directional, quadrilateral/mho characteristicReach accuracy ±5%; timing Zone 2 = 0.4s, Zone 3 = 1.0s
27/59Under/Over VoltagePickup voltage, time delay, AVR interlockPickup ±2%, timing ±20ms
81U/81OUnder/Over FrequencyPickup frequency, time delay, load shedding stepPickup ±0.01 Hz, timing ±10ms
40/64Loss of Field / Ground Fault GeneratorImpedance relay, stator/rotor ground fault detectionSesuai generator protection coordination study
25Synchronizing CheckVoltage, frequency, angle difference window; slip frequencyΔf ±0.05Hz, ΔV ±10%, Δangle ±20°
💡 Catatan IEC 61850 GOOSE Testing: GI modern berbasis IEC 61850 membutuhkan pengujian tambahan: GOOSE message subscription/publication, dataset mapping, schema validation, dan latency test (<4ms untuk protection GOOSE). Omicron CMC 356 dengan license IEC 61850 dapat melakukan full GOOSE simulation testing — PT TEM memiliki kemampuan ini.

HV Apparatus Testing

CT, CVT & Circuit Breaker Testing — Parameter dan Metode per IEC

⚡ Current Transformer (CT) Testing

ParameterMetodeStandar
Ratio TestCPC 100 atau CT Analyzer — inject primer, baca sekunderIEC 61869-2 ±0.1%
Polarity CheckDC impulse method atau primary injection polaritasIEC 61869-1
Burden TestLoad VA pada terminal sekunder saat rated currentRated burden ±10%
Excitation CurveInject tegangan sekunder, plot V vs I (knee point)IEC 61869-2 Annex 2C
Insulation TestMegger 5kV primer vs sekunder, primer vs ground≥1000 MΩ
Phasing Test3-phase simultaneous dengan referensi sinyalSesuai wiring diagram

Testing CT (Current Transformer) 150kV di switchyard gardu induk PLN oleh PT TEM — uji rasio, burden, akurasi kelas 5P20

Testing CT gardu induk 150kV — verifikasi rasio, burden, dan polaritas CT sebelum komisioning relay

⚡ Circuit Breaker (CB) Testing

ParameterMetodeAcceptance Criteria
Close TimeCB Analyzer — waktu perintah close hingga kontak menyentuh≤80ms (IEC C37.09)
Trip TimeCB Analyzer — waktu perintah trip hingga kontak membuka≤50ms tipe normal; ≤30ms tipe cepat
O-C-O (Reclose)Full reclose cycle measurementSesuai spesifikasi CB
Contact ResistanceDLRO 200A — ukur resistance main contact<100μΩ (100kV+) atau sesuai name plate
Insulation (Megger)Megger 5kV antar fasa, antar kontak open CB≥1000 MΩ
SF6 PressureBuilt-in pressure gauge atau SF6 analyzer eksternalNominal pressure ±5% sesuai rating sheet
Min. Trip VoltageTurunkan tegangan DC trip coil — catat minimum voltage trip≤70% rated voltage DC

Testing circuit breaker 150kV di gardu induk — PT TEM melakukan CB analyzer test, timing measurement, dan contact resistance test

Testing circuit breaker 150kV di gardu induk — CB analyzer test, timing measurement, dan contact resistance oleh PT TEM

Testing CVT (Capacitive Voltage Transformer) gardu induk 150kV oleh PT TEM — uji rasio tegangan dan tan delta CVT

Testing CVT (Capacitive Voltage Transformer) gardu induk 150kV — uji rasio tegangan, tan delta, dan burden CVT

Testing baterai DC gardu induk 150kV — uji kapasitas, discharge test, dan verifikasi sistem DC supply untuk relay dan kontrol

Testing baterai DC gardu induk 150kV — uji kapasitas, discharge test, dan verifikasi DC supply untuk relay dan kontrol

Portofolio & Referensi

Referensi Proyek T&C Gardu Induk PT TEM di Lapangan

PT TEM telah mengerjakan testing commissioning HV apparatus dan relay protection di puluhan proyek GI 150kV di seluruh Indonesia — dari GI PLN transmisi hingga substation industri migas, smelter, dan pembangkit swasta.

🔵

GI 150kV PLN — Kalimantan

Testing commissioning GI 150kV PLN wilayah Kalimantan Timur dan Kalimantan Selatan. Relay protection (SIPROTEC, REF615), CT testing, CB timing, energize support.

🟡

GI 150kV Pasaman Barat — Sumatera Barat

Testing commissioning GI 150kV SUTT Pasaman Barat. Energize first power dilaksanakan setelah semua T&C pass. Dokumentasi foto tersedia.

🟠

Gardu 20kV Pertamina Cepu

Commissioning substation 20kV Pertamina EP Cepu — relay testing, CT ratio test, CB analyzer, dan energize support di fasilitas migas operasional.

⚙️

Substation IMIP Morowali — Smelter Nikel

Testing komisioning relay dan HV apparatus di substation smelter nikel IMIP Morowali, Sulawesi Tengah — lingkungan industri berat.

🔥

PLTU Suralaya 9 & 10

Testing dan commissioning generator proteksi PLTU Suralaya — relay differential (87G), loss of field (40), negative sequence (46), dan generator step-up trafo.

⚡

PLTGU Riau

Commissioning sistem proteksi PLTGU (Combined Cycle Gas Turbine) di Riau — relay generator, trafo step-up, bay incoming 150kV.

Commissioning gardu 20kV Pertamina Cepu oleh PT TEM — testing relay dan peralatan HV apparatus di fasilitas migas

Commissioning gardu 20kV Pertamina Cepu — testing relay dan HV apparatus di fasilitas migas operasional

Energize pertama Gardu Induk 150kV Pasaman Barat — PT TEM mendampingi commissioning akhir dan energisasi GI oleh tim PLN

Energize pertama GI 150kV Pasaman Barat — PT TEM mendampingi commissioning akhir bersama tim PLN

FAQ

Pertanyaan Umum — T&C HV Apparatus & Relay Protection GI 150kV

Apa saja tahapan testing commissioning gardu induk 150kV sesuai standar PLN?

Tahapan T&C GI 150kV sesuai SPLN T5.005: (1) Pre-commissioning — insulation resistance, contact resistance, CT/VT ratio, SF6 check; (2) Relay protection testing — secondary injection test semua relay; (3) HV apparatus test — CB timing, CVT tan delta; (4) DC system test — battery capacity, charger; (5) Hipot test kabel dan busbar; (6) Functional test interlocking, SCADA; (7) Step energize bertahap dengan proteksi aktif.

Alat uji apa yang digunakan untuk testing relay protection GI 150kV?

Omicron CMC 356 (secondary injection semua relay digital), Omicron CPC 100+CPTD (primary injection CT dan relay end-to-end), Megger Sverker 900 (relay elektromekanik), DLRO (contact resistance CB), CB Analyzer (timing dan travel), CT Analyzer (ratio dan excitation), Hipot Resonant/VLF (kabel dan busbar), DC battery discharge tester.

Berapa lama durasi testing commissioning gardu induk 150kV baru?

GI single busbar 4 bay: 2–3 minggu. GI double busbar 8 bay: 4–6 minggu. GIS full dengan trafo tenaga: 6–10 minggu. Estimasi akurat diberikan setelah PT TEM menerima data peralatan, SLD, dan relay setting list proyek.

Standar apa yang digunakan PT TEM untuk T&C gardu induk?

SPLN T5.005:2018 (PLN), IEC 62271 (HV switchgear), IEC 61869 (CT/VT), IEC 60255 (relay protection), IEEE C57.13 (CT), IEEE C37 (CB), IEC 60840 (kabel HV), IEC 62440/62271 (GIS). Laporan diterbitkan format PLN untuk proses izin operasi.

Apakah PT TEM bisa mengerjakan T&C GI di luar Kalimantan?

Ya. PT TEM sudah mengerjakan T&C GI di Kalimantan, Sumatera (Pasaman Barat, Dumai), Jawa (Pertamina Cepu, PLTU Suralaya), Sulawesi (IMIP Morowali), dan Papua (Timika). Mobilisasi ke seluruh Indonesia via darat, udara, atau laut.

Butuh Jasa Testing Commissioning Gardu Induk 150kV?

PT TEM siap mobilisasi tim engineer bersertifikat lengkap dengan alat uji Omicron CMC 356, CPC 100, CB Analyzer, dan hipot resonant ke lokasi GI Anda di seluruh Indonesia. Konsultasi gratis — kirim SLD dan relay list proyek Anda sekarang.

Layanan Terkait

💬 Tanya Tim PT TEM Kami siap bantu informasikan:
Scroll to Top